Formwork Striking Times: When Can Formwork Be Removed?

Formwork can be struck only when the concrete has gained enough strength. Strength, not the calendar, is the test. Vertical faces usually come off long before slab and beam soffits, which carry the concrete’s weight. On UK sites, removal is authorised through the temporary works procedure.

What does “striking” formwork mean?

Striking means removing formwork, and sometimes its supporting falsework, after a concrete pour. It is a planned step, not a tidy-up job. Strike too early and you risk damaging the concrete, or leaving a structure that cannot yet carry its loads.

Formwork shapes the wet concrete, while falsework holds it up. If the difference is unclear on your site, read our guide to formwork vs falsework. Both are temporary works and both need controlled removal.

What decides when formwork can be struck?

No single number of days fits every pour. Designing Buildings notes that air temperature, humidity and curing rate all affect removal time (Designing Buildings). The main factors are:

  • Concrete strength at the time of striking. Formwork comes off once the concrete has gained enough strength. Age is only a rough guide to strength.
  • Element type. Wet concrete pressure on wall and column faces falls to zero within hours. Slab and beam soffits carry the concrete’s weight.
  • Temperature. Cold concrete gains strength more slowly than warm concrete (Ecocem).
  • Cement type. Blends with GGBS can gain early strength more slowly, especially in very cold weather and thin sections (Ecocem).
  • Loads after striking. Temporary structures must withstand any foreseeable loads (HSE). Wind is one of them, and the Harrison report includes a method for the strength needed to resist wind loading.
  • Surface damage. Striking vertical faces too early can cause mechanical damage (Ecocem, citing CIRIA Report 136).

Vertical vs soffit formwork: what is the difference?

Vertical formwork holds the sides of walls, columns and beams. Designing Buildings says the wet concrete’s side pressure falls to zero within several hours, depending on setting and curing. That is why faces can come off early.

Soffit formwork supports the underside of slabs and beams. It carries the weight of the concrete until the member can support itself. That is why soffits and props stay in much longer.

Formwork type What it supports Main striking risk Usual sign-off
Wall and column faces Side pressure from wet concrete Mechanical damage to faces Strength check before striking
Beam sides Side pressure only Mechanical damage to faces As for vertical faces
Slab and beam soffits Self-weight of concrete plus loads Member not yet strong enough to carry loads Authorisation to remove under the temporary works procedure
Props Slabs and beams above Removing support too soon Authorisation to remove under the temporary works procedure

What striking figures do published sources give?

Some guidance does quote figures. Treat them as background reading, not a site rule. Your temporary works design and project specification always take priority.

Element Published figure Conditions and source
Vertical formwork Minimum 5 N/mm² recommended “In all cases” when striking vertical formwork (Designing Buildings)
Vertical formwork 2 N/mm² or more to prevent mechanical damage CIRIA Report 136, as cited by Ecocem
Vertical formwork 12 hours At 16°C and above, BS 8110 (now withdrawn) as cited by Ecocem
Slab soffit formwork 4 days, or earlier at 10 N/mm² or twice the slab stress, whichever applies BS 8110 (now withdrawn) as cited by Ecocem
Beam sides 9 to 12 hours Air temperature 7 to 16°C (Designing Buildings)
Beam soffits 8 to 14 days Air temperature 7 to 16°C (Designing Buildings)
Beam props 15 to 21 days Air temperature 7 to 16°C (Designing Buildings)

BS 8110 has been withdrawn and replaced by Eurocode 2 and BS EN 13670, so treat its figures as historical background. The sources do not agree on one vertical strength value. That gap shows why a project-specific decision is needed. Special mixes also change the picture. Holcim’s Strike concrete is sold for striking 4 to 24 hours from casting, depending on temperature and grade (Holcim).

How is concrete strength checked before striking?

Several methods are used to judge striking times. Their advantages and weaknesses are reviewed in Formwork Striking Times by T. A. Harrison.

  • Standard cubes. Easy to run, but cured at 20°C, so they may not match the in-situ concrete (Ecocem).
  • Temperature matched curing (TMC). Cubes cured in water that matches the in-situ temperature give a far more accurate measure (Ecocem).
  • Maturity methods. Temperature history is used to estimate strength gain. The Harrison report includes a maturity calculation using the Sadgrove formula.
  • Prediction software. The Harrison report also reviews methods that predict striking times with computer programs.

Who decides, and where do BS 5975 and BS EN 13670 fit?

HSE describes BS 5975 as one way of managing temporary works. It reflects an industry consensus on good practice, and there is no legal requirement to follow it (HSE temporary works FAQs). HSE lists “authorisation to load and removal” among the coordination tasks. In practice, striking is signed off through your temporary works procedure.

HSE says the Temporary Works Coordinator should have enough authority to stop unsatisfactory work (HSE Temporary Works). BS 5975-1:2024 covers management procedures and BS 5975-2:2024 covers falsework design and implementation. By law, temporary structures must withstand any foreseeable loads, and that applies during striking too.

BS EN 13670 covers execution and workmanship of concrete structures. The Concrete Centre notes Eurocode 2 assumes its requirements are complied with. The National Structural Concrete Specification is named as complementary information in the UK national annex (The Concrete Centre). Check your project’s concrete specification for its striking requirements.

How should striking be done on site?

  1. Confirm written authorisation to strike is in place.
  2. Check strength results meet the figure in the temporary works design.
  3. Strike vertical faces first, releasing ties and adjusters such as a Corner Ratchet in order.
  4. Leave props exactly as the design states.
  5. Mark anything that must stay with pull-tight labelling tags, for example “do not strike”.
  6. Check props, strut bases and any Strut Foot remain secure while nearby panels come out.
  7. Clean, inspect and store reusable kit, and set aside damaged items.

Take care not to damage young concrete by dropping panels or levering hard against faces. Do not stack struck kit on fresh slabs unless the design allows that load.

Buying for a job? Shop falsework accessories and formwork accessories for UK sites, priced on a trade quote.

Buying for this job?

OM Private Ltd supplies Strut Feet, Slab Feet, Corner Ratchets, and all falsework accessories to sites across the UK.

Request a trade quoteCall +44 7452 889827

Trade prices on any quantity · UK-wide delivery · Quote requests 24/7

Frequently asked questions

How long should formwork stay on concrete in the UK?

There is no single answer. Striking depends on concrete strength, temperature, cement type and the element. The temporary works design and the project specification set the requirement for your pour.

Can wall formwork be removed before slab formwork?

Yes, usually. Pressure on wall and column faces falls to zero within hours. Slab soffits carry the concrete’s weight and need props until the slab can support itself.

Does cold weather change formwork striking times?

It can. Cold concrete gains strength more slowly, especially in small or thin sections. Temperature matched cubes give a more accurate check of in-situ strength.

Who authorises formwork removal?

On sites following BS 5975, removal is authorised through the temporary works procedure, usually through the Temporary Works Coordinator. HSE lists authorisation to load and removal as a coordination task. BS 5975 is good practice, not law.

Planning your next pour? Browse our formwork accessories and add items to your quote list, then request a trade quote from OM Private Ltd for supply to sites across the UK.

Sources: Designing Buildings Wiki, Formwork; Ecocem, GGBS Concrete Early Age Strength; T. A. Harrison, Formwork Striking Times; Holcim UK, Strike Concrete; HSE, Temporary Works; HSE, Temporary works FAQs; The Concrete Centre, Standards for workmanship and temporary works