Slab edge formwork is the temporary vertical shuttering that forms the perimeter of a concrete slab. It holds wet concrete to line, level and thickness until it can be struck. A stop end does the same job at a planned break in a pour. On suspended slabs, the edge also needs protection to stop falls.
What is slab edge formwork?
Formwork is a temporary mould that concrete is poured into so it sets to the required shape, as Designing Buildings defines it. Slab edge formwork is the part of that mould that runs around the outside of the slab. It sets the finished edge line, the slab depth and often the top-of-concrete level.
The edge form must resist the pressure of wet concrete without moving or bulging. It must also be removable without damaging the cast edge. Joints should be sealed to stop grout leaking out.
Edge forms can be site-made timber and plywood, steel system forms, or stay-in-place steel profiles. The choice depends on the slab type, edge length, finish needed and how often the form will be reused.
How are slab edges formed on ground-bearing slabs?
A ground-bearing slab sits directly on prepared ground, sub-base or blinding. The edge form is set on that base and held against the outward push of the concrete. Common approaches are listed below.
- Timber shutters with stakes and kickers: boards or ply set to level, pinned into the ground and braced back.
- Proprietary edge brackets on fixing plates: a fixing plate held down with ground nails, as shown in PASCHAL’s slab edge formwork information.
- Stay-in-place steel edge forms: galvanised profiles nailed to the blinding or gravel layer and left in the slab. DYWIDAG describes its RECOSTAL Speed Edge as self-supporting up to 50 cm high.
On ground slabs the main risks are the form kicking out at its base and the edge drifting off line. Check fixings into soft or wet ground carefully before the pour.
How are slab edges formed on suspended slabs?
A suspended slab is cast on a soffit deck carried by falsework, not on the ground. The edge form sits at the perimeter of that deck. It is usually fixed to the deck itself, to the edge beam formwork, or to brackets anchored into the structure below.
PASCHAL’s system, for example, uses a load-bearing slab edge bracket bolted to an anchor cast into the wall below. A slab edge stop slides into the bracket and is tightened against the formwork panel. The same document shows railing posts, toe boards and guard rail parts fitted to the system.
Suspended edges carry two loads at once: concrete pressure and the people working next to an open drop. That is why edge forms and edge protection are often planned together on frame jobs.
| Feature | Ground-bearing slab edge | Suspended slab edge |
|---|---|---|
| What the form sits on | Blinding, sub-base or compacted ground | Soffit deck, edge beam formwork or brackets on the structure below |
| Typical fixing | Stakes, ground nails, fixing plates, kickers | Deck fixings, anchored brackets, ties, clamps or bolts |
| Main failure risk | Base of form kicking out or settling | Form moving outward over an open edge |
| Fall risk at the edge | Usually low, unless next to an excavation or level change | High: edge protection needed for anyone near the open edge |
Edge forms vs stop ends: what is the difference?
An edge form shapes the permanent outside edge of the slab. A stop end closes off a pour where concreting will stop and later restart. The concrete cast against a stop end becomes a construction joint.
Designing Buildings, citing CIRIA C736, describes a construction joint as one formed when placing concrete is interrupted. These are sometimes called daywork joints. Read more in the Designing Buildings concrete joint entry.
Stop ends often have reinforcement passing through them. That makes them harder to seal and brace than a plain edge form. For step-by-step fixing, see our guide on how to fix a stop end.
| Point | Slab edge form | Stop end |
|---|---|---|
| Purpose | Forms the final perimeter of the slab | Forms a planned break between pours |
| Position | Outside edge, openings, steps in level | Within the slab, at agreed joint locations |
| Reinforcement | Usually stops inside the edge cover | Often passes through the stop end |
| Finished result | Exposed or clad slab edge | Construction joint against the next pour |
How is slab edge formwork fixed?
The fixing method must hold the form against concrete pressure and keep it to line until striking. Typical methods on UK sites include:
- Nailing or screwing to the deck with timber kickers and raking braces back to the soffit.
- Anchored brackets bolted into cast-in anchors in the structure below, as in proprietary systems.
- Ties through the form, which help hold a stop end square and to thickness. Our range includes a Timber End Tie.
- Edge attachments fixed to the slab edge itself. We supply an Adjustable Slab Edge Attachment.
- Ground nails and fixing plates for edges cast on blinding or base slabs.
Treat slab edge formwork as temporary works. In the UK these are managed under BS 5975, now published in two parts: BS 5975-1:2024 for management procedures and BS 5975-2:2024 for falsework design and implementation (BSI).
PASCHAL also warns that the formwork must be sized separately and that mixing parts from other makers needs separate checks. Follow the manufacturer’s instructions for any proprietary system.
What edge protection is needed at slab edges during construction?
The Work at Height Regulations 2005 apply to all work at height where a fall could cause personal injury. HSE sets out a simple order: avoid work at height, prevent falls, then minimise the distance and consequences of a fall. Measures that protect everyone come before personal protection, as explained in HSE’s introduction to working at height.
Guardrails at a slab edge are collective protection, because they work without the worker doing anything. A harness is personal protection and only works if the person uses it correctly.
For construction work, HSE gives these guardrail figures in its work at height FAQs and construction FAQs:
- Top guardrail at least 950 mm high.
- Gap between the top rail and any intermediate rail no more than 470 mm.
- Toe boards that are suitable and sufficient, with a minimum 100 mm height given as an acceptable example.
Slab edge barriers are usually posts fixed at the edge, carrying rails, mesh panels or boards. Posts may be cast in, bolted to the edge face or set in a base on the deck. Some proprietary edge attachments state a class under EN 13374. Combisafe, for example, cites EN 13374 Class A for an attachment that can be used on slab edges.
Our Slab Feet are a galvanised post base. Any barrier built from posts and bases must still be designed and checked as a complete system.
What should you check before and after the pour?
- Edge form set to the drawn line, level and slab depth.
- Braces, ties, anchors and fixings complete and tight.
- Joints and gaps sealed to stop grout loss.
- Stop ends at agreed joint positions, with bars correctly placed through them.
- Edge protection in place before anyone works near an open edge.
- Edge protection kept in place, or replaced, when the edge form is struck.
Striking times depend on concrete strength, temperature and the temporary works design. Get the striking sequence agreed before the pour, not after.
Buying for a job? Shop falsework accessories and formwork accessories for UK sites, priced on a trade quote.
Buying for this job?
OM Private Ltd supplies Slab Edge Attachments, Timber End Ties, Slab Feet, and all formwork accessories to sites across the UK.
Request a trade quoteCall +44 7452 889827
Trade prices on any quantity · UK-wide delivery · Quote requests 24/7
Frequently asked questions
Is a stop end the same as slab edge formwork?
No. Slab edge formwork forms the permanent outside edge of a slab, while a stop end closes a pour at a planned construction joint. Both resist wet concrete pressure, but stop ends often have reinforcement passing through them.
What height must slab edge guardrails be in the UK?
For construction work, HSE says the top guardrail should be at least 950 mm high. The gap between the top and intermediate rail should not exceed 470 mm, and toe boards must be suitable and sufficient.
Can slab edge formwork be left in place?
Yes, some steel edge forms are designed to stay in the slab after concreting. Timber and reusable system forms are struck once the concrete has gained enough strength.
Who designs slab edge formwork?
Slab edge formwork is temporary works, so it should be designed and checked under your site’s temporary works procedure. BS 5975-1:2024 covers temporary works management procedures and BS 5975-2:2024 covers falsework design.
OM Private Ltd supplies formwork and falsework accessories to sites across the UK on a trade quote basis. Browse our formwork accessories, add items to your quote list, then request a quote. You can also call +44 7452 889827 or email info@omprivateltd.co.uk.
Sources: HSE – Work at height FAQs; HSE – Introduction to working at height safely; HSE – Construction: work at height; Designing Buildings – Formwork; Designing Buildings – Concrete joint; PASCHAL – Technical information: slab edge formwork; DYWIDAG – RECOSTAL Speed Edge; Combisafe – Flexi attachment