How to Fix a Stop End in Formwork: Step by Step

To fix a stop end, set a board, panel or mesh across the end of the pour at the joint line, hold it square at the right thickness with stop end ties or bracing, and let the reinforcement pass through it where the design calls for continuity. A stop end closes off the edge of a pour so concrete can be cast in sections. It must be strong enough to resist wet concrete pressure, tight enough to stop grout loss, and placed exactly where the designer wants the joint.

What is a stop end?

A stop end is the temporary or permanent closure at the end of a concrete pour, such as at a construction joint in a slab or wall. The next pour is cast against it later.

Types of stop end

Type What it is Notes
Timber stop end Boards or ply cut to fit, often slotted for rebar Cheap and flexible; removed after the pour. The joint face may need preparing before the next pour
Framed panel stop end System formwork panels closed off at the end Held with stop end ties to the panels
Expanded metal (permanent) stop end Ribbed metal mesh left in the concrete Leaves a keyed face for the next pour

HSE reports a London Underground slab where expanded metal stop ends replaced timber. The next section bonded to the metal face “as strong as a traditional scabbled joint”, so no scabbling was needed and workers avoided hand-arm vibration (HSE).

How to fix a stop end: step by step

  1. Check the joint position. Construction joints go where the structural designer allows them. Mark the line before you start.
  2. Cut or set the stop end. Fit boards or mesh tight to the soffit and sides. Slot timber for any bars that run through.
  3. Hold it at the right thickness. Fix it to the side forms with stop end ties, such as our Timber End Tie for framed panels, or with bracing.
  4. Seal the gaps. Close gaps round bars and at the edges so grout does not leak; leaks leave honeycombing at the joint.
  5. Brace against pressure. Wet concrete pushes hardest at the bottom of the pour, so check the stop end will not move or bow.
  6. Fit any waterstop or joint detail the design requires, for example on basement walls.
  7. Strike and prepare. Remove a temporary stop end when the design allows, and prepare the joint face as specified before the next pour.

Common stop end problems

  • Blowouts: the stop end moves under pressure. Fix with enough ties or bracing at the base.
  • Grout loss: gaps round rebar or at the edges. Seal them before the pour.
  • Wrong thickness: the stop end is not held square. Use ties that fix the spacing.
  • Poor bond at the joint: the face was not prepared, or a keyed stop end was not used.

Related guides: slab edge formwork · types of formwork ties · formwork striking times

Buying for this job?

OM Private Ltd supplies Timber End Ties, Panel Hole Plugs, Profile Fixing Plates, and all formwork accessories to sites across the UK.

Request a trade quoteCall +44 7452 889827

Trade prices on any quantity · UK-wide delivery · Quote requests 24/7

Frequently asked questions

What is a stop end tie?

A tie that holds a stop end to the side formwork at the correct thickness, so the edge of the pour stays square and does not blow out.

Can a stop end be left in the concrete?

Yes, if it is a permanent type such as expanded metal. Timber and panel stop ends are removed after the pour.

Where should a construction joint go?

Where the structural designer specifies. Joint positions affect strength and watertightness, so they should not be moved on site without approval.

Do I need to scabble a construction joint?

A joint face usually needs preparing so the next pour bonds well. A keyed permanent stop end, such as expanded metal, can avoid scabbling, as in the HSE case study.

Setting out stop ends? See our Timber End Tie, Panel Hole Plugs and formwork accessories, or read types of formwork ties.

Source: HSE, Special formwork avoids scabbling.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top