Types of Formwork: Materials, Uses and Comparison Guide

Formwork is usually grouped by material: timber, plywood, steel, aluminium and plastic, plus permanent (stay-in-place) forms that stay in the structure. Specialist methods such as slipform and jumpform suit tall cores. The right choice depends on how many pours you need, the finish, lifting, labour and budget.

What are the five types of formwork?

There is no single official list. Sources group formwork in slightly different ways, but most group it by the material that forms the mould. Giatec’s comparison covers five materials:

  1. Timber formwork – built on site, adaptable to odd shapes and suited to smaller jobs.
  2. Plywood formwork – sheet material often paired with timber for a smooth finish.
  3. Steel formwork – strong, heavy panels for large projects with many reuses.
  4. Aluminium formwork – lighter metal panels that are quick to assemble and strip.
  5. Plastic formwork – light, moisture-resistant panels for repetitive structures.

Permanent (stay-in-place) formwork is a sixth group. It stays in the finished structure. System (modular) formwork, slipform and jumpform are better seen as methods built from these materials.

How do the main formwork types compare?

The table gives a quick side-by-side view. Reuse figures are only shown where a published source states them.

Type Main material Reuse Typical use Pros Cons
Timber Sawn timber, often with plywood Low – typically 3 to 5 uses (Giatec) Smaller jobs and one-off shapes Adapts to odd shapes; inexpensive for small work; simple to build and strip Labour-intensive; prone to warping and decay; poor for large repeat work
Plywood Water-resistant plywood sheet Limited Often paired with timber Smooth finish; low cost; widely available Vulnerable to water damage; needs careful handling
Steel Steel panels and frames Very high – can be reused hundreds of times (Giatec) Large projects with repeat pours Handles heavy loads; smooth finish High upfront cost; needs lifting equipment; hard to adapt to custom shapes
Aluminium Aluminium panels and frames High – long lifespan Fast-paced projects Light; quick to assemble and strip Costs more than timber; weaker than steel under heavy loads; can react with wet concrete if untreated
Plastic Interlocking or modular plastic panels Multiple uses Quick pours on repetitive structures such as mass housing Moisture-resistant; light to move Limited load capacity; less versatile than timber
System / modular Proprietary panels with matching clamps, ties and props Designed for repeat use Walls and columns Modular parts; can save time on site Must be used within the supplier’s rated limits
Permanent (stay-in-place) Fibre-reinforced plastic, polystyrene (ICF) and others None – stays in the structure Columns, piers, insulated walls No striking; can add protection or insulation Material stays in the structure, so it is not reused
Slipform / jumpform Self-climbing formwork Rises with the structure Cores, shafts, silos, chimneys, bridge pylons Suited to tall vertical work; slipform gives a joint-free finish Jumpform depends on a skilled workforce on site

Timber and plywood formwork

Traditional formwork is timber shuttering built on site from timber and plywood. Designing Buildings calls it relatively easy to produce, but it can be time-consuming for large structures or complex shapes. It is used where labour costs less than reusable steel or plastic formwork.

Shuttering needs a water-resistant grade of plywood. Timber is easy to adapt, but it is prone to warping and decay. Giatec puts its typical life at 3 to 5 uses.

Steel formwork

Steel panels are strong, handle heavy loads and give a smooth finish. Giatec says they can be reused hundreds of times, which suits large projects. The trade-offs are a high upfront cost, the need for lifting equipment and less scope for custom shapes.

Aluminium formwork

Aluminium is light to handle and quick to assemble and strip. Giatec notes a long service life. It costs more than timber and is weaker than steel under heavy loads. Untreated aluminium can also react with wet concrete.

Plastic formwork

Reusable plastic panels interlock or form a modular system for quick pours. Designing Buildings notes they are less versatile than timber because they are prefabricated. They work best on low-cost, repetitive structures such as mass housing. Giatec adds that load capacity is limited.

What is system or modular formwork?

System formwork is a proprietary kit of panels and matching parts. Giatec notes that modular systems can save time on site. For example, RMD Kwikform’s Minima is a lightweight, hand-set modular system for walls and columns. Its kit lists plywood panels, clamps, tie bars and alignment props, with rated concrete pressures for walls and columns.

Formwork on site also relies on smaller accessories, such as:

For the ties that hold opposing faces together, see our guide to types of formwork ties.

What is permanent (stay-in-place) formwork?

Permanent formwork stays in place after the concrete cures. Designing Buildings describes prefabricated fibre-reinforced plastic forms for columns and piers. They remain as permanent axial and shear reinforcement. They also help protect the concrete and reinforcing bars from environmental damage.

Insulated concrete formwork (ICF) is another example. It uses interlocking hollow polystyrene units that stay in place as both formwork and wall insulation.

Slipform and jumpform in brief

Both use self-climbing formwork for tall vertical work such as cores, shafts, chimneys and silos. The formwork is supported by the concrete already cast below it.

  • Slipform moves up continuously at about 300 mm per hour and can give a smooth, joint-free finish. Designing Buildings says it is more economical above seven storeys. It is also used for bridge pylons and piers.
  • Jumpform (climbing) rises in steps, or “jumps”, once the concrete below reaches the strength needed. It is typically used on buildings of more than five storeys and depends on a skilled workforce on site.

How do you choose the right type of formwork?

Start with the number of repeat pours and the finish you need. Then check lifting, handling and labour on site.

  • Few pours or odd shapes: timber and plywood.
  • Many repeat pours: steel, aluminium or a modular system.
  • Lighter handling: aluminium or plastic panels.
  • Insulated walls or protected columns: permanent formwork.
  • Tall cores and shafts: slipform or jumpform.

Whatever you choose, plan the temporary works properly. BS 5975-2:2024 covers the design of falsework and associated formwork. The Concrete Society’s Formwork: a guide to good practice covers materials and equipment, loadings, design, special formwork and work on site.

Buying for this job?

OM Private Ltd supplies formwork clamps (including Claw Head), Strut Feet, Timber End Ties, and all formwork accessories to sites across the UK.

Request a trade quoteCall +44 7452 889827

Trade prices on any quantity · UK-wide delivery · Quote requests 24/7

Frequently asked questions

What are the five types of formwork?

By material, the five usually compared are timber, plywood, steel, aluminium and plastic. Permanent (stay-in-place) formwork is often added as a separate group. System, slipform and jumpform are methods built from these materials.

Which type of formwork can be reused the most?

Giatec’s comparison gives figures only for timber and steel. Steel can be reused hundreds of times. Timber typically lasts 3 to 5 uses.

What is the difference between formwork and falsework?

Designing Buildings describes formwork as the temporary mould that shapes the concrete. Falsework is the props and other supports that hold the formwork in place while the concrete sets. Read more in our guide to formwork vs falsework.

Which British Standard covers formwork design?

BS 5975-2:2024 covers the design of falsework and associated formwork. Together with BS 5975-1:2024, it replaced BS 5975:2019.

Need ties, plugs or strut feet for your next pour? Browse our formwork accessories and add items to your quote list, or request a trade quote for supply to sites across the UK.

Sources: Designing Buildings – Formwork; Designing Buildings – Jumpform v slipform; Designing Buildings – Slip form concrete; Designing Buildings – Insulated concrete formwork; BSI – BS 5975-2:2024; The Concrete Society – Formwork: a guide to good practice; Giatec – Guide to concrete formwork; RMD Kwikform – Minima.